Which of the following would be the impact upon a project if the CPI for the project is .75? seenagape 12 years ago Which of the following would be the impact upon a project if the CPI for the project is .75? A.The project is under-budget. B.There would be a 25 percent cost decrease. C.There would be a 75 percent cost increase. D.The project is over-budget. ← Previous question Next question →