CompTIA Exam Questions

Which of the following would be the effect on the project?

An ongoing project that is currently on schedule has had the required completion date moved up by one week; however, the project scope remains the same. Which of the following would be the effect on the project?

A.
Cost will decrease and time will increase.

B.
Cost will decrease and time will decrease.

C.
Cost will increase and time will increase.

D.
Cost will increase and time will decrease.