Which of the following would be BEST suited to contribu… seenagape 8 years ago A WBS is being developed for a project. Which of the following would be BEST suited to contributecost and time estimates for the project activities? A. Project team members B. Project sponsor C. Project manager D. Project scheduler ← Previous question Next question →