Which of the following would be a direct output of the initiating process group?

Which of the following would be a direct output of the initiating process group? (Select Two).

A.
Project charter

B.
Project management plan

C.
Statement of Work (SOW)

D.
Work Breakdown Structure (WBS)

E.
Preliminary scope statement

Explanation: