Which of the following would be a direct output of the initiating process group? seenagape 10 years ago Which of the following would be a direct output of the initiating process group? (Select Two). A.Project charter B.Project management plan C.Statement of Work (SOW) D.Work Breakdown Structure (WBS) E.Preliminary scope statement Explanation: ← Previous question Next question →