CompTIA Exam Questions

Which of the following will the project manager do to determine the change’s effect on the project

A stakeholder wants to add another requirement to the deliverable. Which of the following
will the project manager do to determine the change’s effect on the project?

A.
Filling out a change control

B.
Performing an impact analysis

C.
Identifying a change

D.
Coordinating with stakeholders to select the course of action

Explanation: