Which of the following tools would be the BEST to use? seenagape 10 years ago A project manager is performing activity duration estimation. This project will have conditionaldecisions. Which of the following tools would be the BEST to use? A.GERT B.Gantt chart C.PERT D.EVM Explanation: ← Previous question Next question →