CompTIA Exam Questions

Which of the following tools is the project manager using?

A project manager is completing a project schedule network diagram using dummy activities to
show all logical relationships. Which of the following tools is the project manager using?

A.
ADM

B.
WBS

C.
AON

D.
PDM

Explanation: