which of the following shows when risks should be reassessed?

During a project, which of the following shows when risks should be reassessed?

A.
Throughout the project lifecycle

B.
Risks should be reviewed during lessons learned

C.
A risk reassessment should occur at project closeout

D.
When a risk has become an issue and has to be acted upon