Which of the following shows the interdependencies between activities on a project schedule? seenagape 8 years ago Which of the following shows the interdependencies between activities on a projectschedule? A. Milestone chart B. Pareto diagram C. Network diagram D. Scatter diagram ← Previous question Next question →