Which of the following shows a project that is presently over its financial budget? seenagape 10 years ago Which of the following shows a project that is presently over its financial budget? A.CPI = 1.4 B.CPI = 0 C.CV = +$11,000 D.CPI = 0.8 Explanation: ← Previous question Next question →