A project stakeholder wants to make changes to a project after work on the project has
already started. Which of the following should the project manager do FIRST?
A.
Submit stakeholder’s change request to the change control board
B.
Perform an analysis on the requested change submitted by the stakeholder
C.
Assign the request a tracking number and record in change request log
D.
Recruit new project team members to expedite the change’s completion date