Which of the following should the project manager consider FIRST?

A project manager is working with a large team on an important project. Many of the team members work remotely. The project manager requires each team member to submit weekly status reports at a certain time each week. One team member consistently submits late status reports. Which of the following should the project manager consider FIRST?

A.
Time zones for various work locations

B.
Necessity of weekly status reports

C.
Format of the status report

D.
Past performance reviews of the team member