Which of the following should be included in a Gantt chart to analyze a project schedule? seenagape 10 years ago Which of the following should be included in a Gantt chart to analyze a project schedule? (SelectThree). A.Risks B.Probability C.Cost analysis D.Start date E.Activity durations F.Finish date Explanation: ← Previous question Next question →