Which of the following scheduling algorithms establishes floats, durations, and paths between work s seenagape 9 years ago Which of the following scheduling algorithms establishes floats, durations, and pathsbetween work schedule activities? A. AON B. PERT C. CPM D. GERT ← Previous question Next question →