Which of the following represents the ETC of this project? seenagape 11 years ago In a highway project 5 miles (8 kilometers) out of the total 15 miles (24 kilometers) have been completed. The BAC is $900,000. Which of the following represents the ETC of this project? A.$150,000 B.$300,000 C.$450,000 D.$600,000 ← Previous question Next question →