Which of the following represents the EAC of an ongoing project with an AC of $100,000, a CV of $10 seenagape 11 years ago Which of the following represents the EAC of an ongoing project with an AC of $100,000, a CV of $10,000 and an ETC of $50,000? A.$90,000 B.$140,000 C.$150,000 D.$160,000 ← Previous question Next question →