Which of the following is the CPI of the project? seenagape 12 years ago An ongoing project has a BAC of $450,000, an EV of $110,000 and an AC of $100,000. Which of the following is the CPI of the project? A.$340,000 B.1.1 C.$10,000 D..91 ← Previous question Next question →