Which of the following is the correct progression of the project life cycle?
A.
Planning, Initiating, executing, monitoring / controlling, closing
B.
Initiating, planning, executing, monitoring / controlling, closing
C.
Planning, Initiating, monitoring / controlling, executing, closing
D.
Initiating, planning, monitoring / controlling, executing, closing