Which of the following estimating types requires the MOST effort when creating a work breakdown stru seenagape 10 years ago Which of the following estimating types requires the MOST effort when creating a work breakdownstructure (WBS)? A.Expert judgment B.Top-down C.Bottom-up D.Rough order of magnitude Explanation: ← Previous question Next question →