Which of the following elements are essential for this system to be effective?

A project manager seeks to implement a change control system. Which of the following elements
are essential for this system to be effective? (Select THREE).

A.
Change request form

B.
Approval mechanism

C.
Pareto chart

D.
Impact analysis

E.
Earned Value (EV) analysis