Which of the following documents would MOST likely be impacted? seenagape 12 years ago A project manager receives a request for a minor change to one of the deliverables. Which of the following documents would MOST likely be impacted? A.Work Breakdown Structure (WBS) B.Project charter C.Communication plan D.Quality plan ← Previous question Next question →