Which of the following documents would include this information? seenagape 12 years ago A project manager is reviewing the ownership, date, and the necessary training for a deliverable. Which of the following documents would include this information? A.Transition plan B.Quality plan C.Change Control plan D.Procurement plan ← Previous question Next question →