Which of the following documents would a project manager review to determine all the identified risk seenagape 10 years ago Which of the following documents would a project manager review to determine all the identifiedrisks on a project? A.Risk matrix B.Risk register C.Risk response D.Risk baseline Explanation: ← Previous question Next question →