Which of the following documents should be updated? seenagape 11 years ago The change control board approved a request for $25,000 to address rising labor costs ofspecialized trades. Which of the following documents should be updated? A.Scope statement B.Project schedule C.Resource requirements D.Project budget ← Previous question Next question →