which of the following documents? seenagape 11 years ago The project manager can use the lowest level of the risk breakdown structure (RBS) to createwhich of the following documents? A.Risk register B.Risk checklist C.Probability and impact matrix D.Risk budget Explanation: ← Previous question Next question →