Which of the following describes the LOWEST level of a work breakdown structure (WBS)? seenagape 11 years ago Which of the following describes the LOWEST level of a work breakdown structure (WBS)? A.Technical specifications B.Project performance reports C.Work packages D.Functional specifications Explanation: ← Previous question Next question →