Which of the following cost estimating techniques uses previous, similar projects as a basis of esti seenagape 10 years ago Which of the following cost estimating techniques uses previous, similar projects as a basis ofestimating costs for the current project? A.Top-down estimating B.Parametric estimating C.Bottom-up estimating D.Analogous estimating Explanation: ← Previous question Next question →