A project manager has noticed low attendance at weekly meetings for a new project. Which
of the following can the project manager do to improve meeting attendance?
A.
Cancel the meetings because of a lack of attendance.
B.
Address all issues as they arise during the meeting.
C.
Start and end the meetings on time.
D.
End the meetings when all topics have been discussed.