Which of the following BEST describes the situation? seenagape 12 years ago Several managers are sharing a project team member, which is impacting the progress of both projects. Which of the following BEST describes the situation? A.Varying work styles B.Schedule variance C.Scope creep D.Competing resource demands ← Previous question Next question →