CompTIA Exam Questions

Which of the following activity sequencing techniques uses nodes to symbolize the dependencies of ea

Which of the following activity sequencing techniques uses nodes to symbolize the
dependencies of each activity?

A.
Gantt Chart Method

B.
Critical Path Method

C.
Critical Chain Method

D.
Arrow Diagramming Method