Which of the following activities would happen FIRST in procurement management? seenagape 12 years ago Which of the following activities would happen FIRST in procurement management? A.Request seller responses. B.Perform a make or buy analysis. C.Perform contract administration. D.Perform vendor selection. ← Previous question Next question →