CompTIA Exam Questions

Which of the following actions should the project manager perform FIRST?

An unexpected risk has been identified in a project. Which of the following actions should
the project manager perform FIRST?

A.
Perform a risk qualitative analysis

B.
Add the risk to the risk register

C.
Update the project probability / impact matrix

D.
Submit a change request