This is an example of:

During a code review a software developer discovers a security risk that may result in hundreds of hours of
rework. The security team has classified these issues as low risk. Executive management has decided that the
code will not be rewritten. This is an example of:

A.
Risk avoidance

B.
Risk transference

C.
Risk mitigation

D.
Risk acceptance