This could have been avoided by using: seenagape 9 years ago A project is struggling because the sponsor continually has to increase funding which maycause the project to get cancelled. This could have been avoided by using: A. AWBS. B. Change control. C. Quality metrics. D. Fixed costs. ← Previous question Next question →