CompTIA Exam Questions

The work breakdown structure (WBS) dictionary contains which of the following elements? (Select THRE

The work breakdown structure (WBS) dictionary contains which of the following elements? (Select THREE).

A.
Identification of stakeholders

B.
Description of work processes and procedures

C.
Quality control processes

D.
Estimated calendar time of activities

E.
Required resources

F.
Risk response strategies