PrepAway - Latest Free Exam Questions & Answers

Tag: Exam PK0-003 (updated April 10th, 2014)

Exam PK0-003: CompTIA Project+ (updated April 10th, 2014)

Which of the following is the NEXT step the project manager should take to keep the project on schedule?

A key team member is performing poorly on a project. The project manager has verified that the
team member knows the project expectations. The project manager has met repeatedly with this
team member to outline expectations. Which of the following is the NEXT step the project
manager should take to keep the project on schedule?


Page 4 of 36« First...23456...102030...Last »