If the SPI and CPI are both above 1, then the project is: seenagape 9 years ago If the SPI and CPI are both above 1, then the project is: A. Ahead of schedule and over budget. B. Ahead of schedule and under budget. C. Behind schedule and over budget. D. Behind schedule and under budget. ← Previous question Next question →