Given the schedule estimates of Best Case = 2 days… seenagape 9 years ago Given the schedule estimates of Best Case = 2 days, Worst Case = 12 days, and MostLikely = 4 days, calculate PERT. A. 8 days B. 6 days C. 4 days D. 5 days ← Previous question Next question →