Which of the following risk response strategies was applied in this circumstance?

A qualitative analysis identified a server crash as an internal project risk with a medium probability
and high adverse impact to the project. The project manager decides to manage this risk by
authorizing the purchase and installation of a tape backup unit for the server, to prevent the
potential loss of documents. Which of the following risk response strategies was applied in this

circumstance?