Which of the following is the FIRST technique the project manager can use to define their roles?
Project team members are confused about their roles on a project. Which of the following is the
FIRST technique the project manager can use to define their roles?
Which of the following is the role of the board?
A project manager is responsible for meeting with the company project review board to periodically
evaluate the progress on a project. Which of the following is the role of the board?
In order to obtain the Best pricing and product quality, a project manager should:
In order to obtain the Best pricing and product quality, a project manager should:
which of the following should be considered FIRST?
A project manager has a project with staff in four different countries. When generating the
resource management plan, which of the following should be considered FIRST?
Which of the following resource leveling techniques describes schedule compression by performing activities co
Which of the following resource leveling techniques describes schedule compression by
performing activities concurrently?
Which of the following conflict resolution styles is being used?
Two team members refuse to work together and have undermined the project with their constant
bickering. The project manager needs both of them to complete the project. The team members
meet and agree to work at different times. Which of the following conflict resolution styles is being
used?
Which of the following cost estimating techniques was used?
A project manager creates a detailed list of costs for each activity involved in the project and then
uses the sum of the individual activities to create the budget. Which of the following cost
estimating techniques was used?
How many total communication paths exist after the addition of resources?
A project team has increased from six to twelve resources. How many total communication paths
exist after the addition of resources?
Which of the following is included in the project scope document?
Which of the following is included in the project scope document? (Select TWO).
Who of the following determines if the project continues?
A project manager has finished the first phase of a project. Who of the following determines if the
project continues?