Which of the following would be the BEST tool to estimate the final duration?
A project team is estimating the amount of time needed to perform an activity. They have recommended an optimistic, pessimistic, and most likely duration to complete the activity. Which of the following would be the BEST tool to estimate the final duration?
Which of the following is MOST likely to be included in a communication plan?
Which of the following is MOST likely to be included in a communication plan?
This is an example of which of the following types of dependencies? (Select TWO)
In order to meet governmental requirement Q555, all materials must meet spec #A-223 qualifications. This is an example of which of the following types of dependencies? (Select TWO).
Which of the following may require a modification to the project scope baseline?
Which of the following may require a modification to the project scope baseline?
Which of the following is the MOST common relationship used, when constructing a project schedule network diag
Which of the following is the MOST common relationship used, when constructing a project schedule network diagram?
Which of the following sequences represents the correct order for implementing a change request?
Which of the following sequences represents the correct order for implementing a change request?
Which of the following conflict resolution techniques is being used by the project manager?
Although there is a difference of opinion among several team members, the project managers authority is used to keep the project moving forward. Which of the following conflict resolution techniques is being used by the project manager?
Which of the following conflict resolution techniques is described as having one of the conflicting parties no
Which of the following conflict resolution techniques is described as having one of the conflicting parties not deal with the problem?
Which of the following dependencies is demonstrated between task 1 and task 2 in the following diagram?
Refer to the attached Exhibit. Which of the following dependencies is demonstrated between task 1 and task 2 in the following diagram?
The greatest amount of conflict occurs in which of the following team development stages?