Which of the following cost estimating techniques was used?
A project manager creates a detailed list of costs for each activity involved in the project and then uses the sum of the individual activities to create the budget. Which of the following cost estimating techniques was used?
Which of the following are components of an internal / external communication plan? (Select Two).
Which of the following are components of an internal / external communication plan? (Select Two).
Which of the following is the role of the board?
A project manager is responsible for meeting with the companys project review board to periodically evaluate the progress on a project. Which of the following is the role of the board?
Which of the following will MOST likely increase?
A network diagram shows two critical paths for a project. Which of the following will MOST likely increase?
Which of the following tools can the project manager use to show the improbability of the proposed timeline?
A project sponsor is adamant that a complex project must be completed within 12 months. Based on lessons learned from previous projects of this type, the project manager believes that the project cannot possibly finish in less than 24 months. Which of the following tools can the project manager use to show the improbability of the proposed timeline?
The amount of time ahead or behind schedule on a project is called the:
The amount of time ahead or behind schedule on a project is called the:
Which of the following will the project manager use to determine the budgeted cost of work scheduled?
A project manager is managing a project that is scheduled to take ten months to complete. The project is in its sixth month and $450,000 has been spent. The project budget is $990,000. Which of the following will the project manager use to determine the budgeted cost of work scheduled?
In which of the following documents should the project manager record this information?
A key stakeholder on a project advises the project manager that there is a component of the project that has yet to be decided. They are concerned that their needs regarding this component will not be addressed. In which of the following documents should the project manager record this information?
Which of the following would BEST help the project manager?
A project manager is new to an organization and is about to begin work on a $1,000,000 project. Which of the following would BEST help the project manager?
Which of the following is the earned value (EV)?
The project cost performance index is 1.2 and the project manager has spent $71,248 dollars to date. The project is currently 50 percent complete. Which of the following is the earned value (EV)?