Which of the following are the benefits of a work breakdown structure (WBS)? (Select Two).
Which of the following are the benefits of a work breakdown structure (WBS)? (Select Two).
If the EV is $3,000 and the AC is $4,000, which of the following is the CV for the project?
If the EV is $3,000 and the AC is $4,000, which of the following is the CV for the project?
Which of the following would be the impact upon a project if the CPI for the project is .75?
Which of the following would be the impact upon a project if the CPI for the project is .75?
If the EV is $3,000 and the AC is $4,000, which of the following would be the CPI for the project?
If the EV is $3,000 and the AC is $4,000, which of the following would be the CPI for the project?
Which of the following conflict resolution styles is being used?
Two team members refuse to work together and have undermined the project with their constant bickering. The project manager needs both of them to complete the project. The team members meet and agree to work at different times. Which of the following conflict resolution styles is being used?
Which of the following is the NEXT step the project manager should take?
A new critical requirement has been identified after the project charter was approved. Which of the following is the NEXT step the project manager should take?
Which of the following is a characteristic of fast-tracking a project?
A stakeholder has indicated that a three phase project must be completed in four months instead of the previously agreed upon six months. It is determined that fast-tracking the project is the only option. Which of the following is a characteristic of fast-tracking a project?
The twelve consecutive points represent which of the following?
A quality control technician is diagramming test results on a run chart. The chart consists of twenty-five points, with twelve consecutive points below the median line; however, the other thirteen points alternate above and below the median line. The twelve consecutive points represent which of the following?
In order to compare a current projects quality to that of a previously completed project, a project manager sh
In order to compare a current projects quality to that of a previously completed project, a project manager should use which of the following techniques?
Cause and effect diagrams are also referred to as:
Cause and effect diagrams are also referred to as: