Which of the following datacenter elements is being designed?
The datacenter design team is implementing a system, which requires all servers installed in racks
to face in a predetermined direction. AN infrared camera will be used to verify that servers are
properly racked. Which of the following datacenter elements is being designed?
Which of the following is an effective way to ensure the BEST temperature for all equipment within a datacente
Which of the following is an effective way to ensure the BEST temperature for all equipment within
a datacenter?
Which of the following is an effective way to ensure the BEST temperature for all equipment within a datacente
Which of the following is an effective way to ensure the BEST temperature for all equipment within
a datacenter?
Which of the following results in datacenters with failed humidity controls?
Which of the following results in datacenters with failed humidity controls? (Select TWO).
Which of the following results in datacenters with failed humidity controls?
Which of the following results in datacenters with failed humidity controls? (Select TWO).
Which of the following environmental problems may occur?
The datacenter manager is reviewing a problem with a humidity factor that is too low. Which of the
following environmental problems may occur?
Which of the following environmental problems may occur?
The datacenter manager is reviewing a problem with a humidity factor that is too low. Which of the
following environmental problems may occur?
Which of the following would reduce the connectivity issues?
A technician is investigating intermittent switch degradation. The issue only seems to occur when
the building’s roof air conditioning system runs. Which of the following would reduce the
connectivity issues?
This caused the electronic locks on the datacenter door to release because the:
A malicious person gained access to a datacenter by ripping the proximity badge reader off the
wall near the datacenter entrance. This caused the electronic locks on the datacenter door to
release because the:
Drag and drop the appropriate security controls on the floor plan.
DRAG DROP
You have been tasked with designing a security plan for your company. Drag and drop the
appropriate security controls on the floor plan.
Instructions: All objects must be used and all place holders must be filled. Order does not matter.
When you have completed the simulation, please select the Done button to submit.