All of the following are taken into account when determining the critical path EXCEPT: seenagape 11 years ago All of the following are taken into account when determining the critical path EXCEPT: A.Late start and finish dates. B.Activity durations. C.Early start and finish dates. D.Resource limitations. Explanation: ← Previous question Next question →