CompTIA Exam Questions

All of the following are inputs to project schedule development EXCEPT:All of the following are inpu

All of the following are inputs to project schedule development EXCEPT:All of the following are
inputs to project schedule development EXCEPT:

A.
change requests

B.
lead- and lag-times.

C.
resource requirements.

D.
resource availability.