Which three factors should you consider when recommending a maintenance window to execute a rollout

Which three factors should you consider when recommending a maintenance window to execute a
rollout plan that is received from engineering? (Choose three.)

A.
service level agreements

B.
network capacity management

C.
key performance indicators

D.
time of day

E.
customer impact