Which task is conducted during the develop the systems acceptance test plan activity?

.Which task is conducted during the develop the systems acceptance test plan activity?

A.
Turn-up And Commission Tests

B.
Create Logical topology diagrams

C.
Network Resilience Tests

D.
Compare Test Parameters Against Service Level Requirements