Which task is conducted during the develop the systems acceptance test plan activity?

Which task is conducted during the develop the systems acceptance test plan activity?

A.
create logical topology diagrams

B.
turn-up and commission tests

C.
network resilience tests

D.
compare test parameters against service level requirements