The Project Kick-off in the pan phase provides an opportunity to complete which tow of the following tasks? ( Choose two)

A.
Confirm Project roles and responsibilities

B.
Perform preliminary application discovery

C.
Understand workflow between departments

D.
Confirm project and milestone dates

E.
Perform detailed analysis of customer requirements